Question: Question 12 (3 points) A master production schedule shows the following information: MPS Week Week Week Week Beginning inventory - 100 1 2 3 4

Question 12 (3 points) A master production

Question 12 (3 points) A master production schedule shows the following information: MPS Week Week Week Week Beginning inventory - 100 1 2 3 4 Forecast 500 550 400 500 Actual customer orders 550 600 500 450 Projected on-hand inventory Available to promise MPS Using a lot-for-lot rule, what is the MPS quantity for week 4? 50 500 450 0400 Question 13 (3 points)