Question: Question 12 A project has the following earned value data assessed: o Actual Cost (AC): $ 4,000,000 o Cost variance (CV): $-500,000 o Schedule Performance

Question 12 A project has the following earned
Question 12 A project has the following earned value data assessed: o Actual Cost (AC): $ 4,000,000 o Cost variance (CV): $-500,000 o Schedule Performance Index (SPI): 1.12 o Budget at completion (BaC): $ 9,650,000 What is the Earned Value (EV) of the project? $3,500,000 $4,480,000 $5,650,000 $3,000,000 A Moving to another question will save this response. 4,050 14