Question: Question 12 In Plan Risk Management, you define how to conduct risk management activities for a project because careful and explicit planning enhances the probability

Question 12 In Plan Risk Management, you define how to conduct risk management activities for a project because careful and explicit planning enhances the probability of success for the subsequent risk management processes. In this context, what will you NOT do when you Plan Risk Management? Identify Risks Establish an agreed-upon basis for evaluating risk Ensure that the degree, type, and visibility of risk management are commensurate with both the risks and the importance of the project Provide sufficient resources and time for risk management activities