Question: Question 12 When a project has a negative NPV and a positive IRR it means: O Negative NPV means cash is only fully recovered when
Question 12 When a project has a negative NPV and a positive IRR it means: O Negative NPV means cash is only fully recovered when adding salvage value to annual cash flows O Negative NPV means there is a negative IRR O IRR for the project is positive but less than the cost of capital