Question: QUESTION 13 1 points Save Answer Given the following information, develop a material requirements plan that will lead to 400 units of product P being

QUESTION 13 1 points Save Answer Given the

QUESTION 13 1 points Save Answer Given the following information, develop a material requirements plan that will lead to 400 units of product P being available at the beginning of week 7. Product Structure Tree Inventory Information P Scheduled Recpt (wk) A B Item P A B D Currently On-Hand 0 100 0 90 50 Lead Time 1 1 1 2. 2 Order Qty L4L L4L Fixed Q = 450 Fixed Q = 600 L 4L 100 (wk 2) 80 (wk 2) D(2)