Question: Question 13 (2 points) After risk response planning is complete, risk register updates are done. Which of the following is unlikely to be updated in
Question 13 (2 points)
After risk response planning is complete, risk register updates are done. Which of the following is unlikely to be updated in the risk register after response planning?
Question 13 options:
|
| Budget and schedule activities required to implement the chosen responses |
|
| Agreed-upon response strategies |
|
| Project charter updates |
|
| Triggers, symptoms, and warning signs of risks' occurrence |