Question: Question 13 (3.03 points) If four workers (1 worker for each task) were assigned to the four task assembly line shown below, what would be

Question 13 (3.03 points)

Question 13 (3.03 points) If four workers (1

If four workers (1 worker for each task) were assigned to the four task assembly line shown below, what would be the efficiency of the worker doing Task B?

Question 13 options:

Unable to calculate

71%

100%

43%

Question 14 (3.03 points)

If the Forecast for the previous month is 16 and the actual demand is 17. What is the Exponential Smoothing forecast for the next month using a smoothing constant (alpha) of 0.4?

Question 14 options:

14.4

14.2

14.6

12.8

16.2

A Four-Task Assembly Line B D 5 minutes 7 minutes 3 minutes 3 minutes

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!