Question: Question 13 (3.03 points) If four workers (1 worker for each task) were assigned to the four task assembly line shown below, what would be
Question 13 (3.03 points)

If four workers (1 worker for each task) were assigned to the four task assembly line shown below, what would be the efficiency of the worker doing Task B?
Question 13 options:
| Unable to calculate | |
| 71% | |
| 100% | |
| 43% |
Question 14 (3.03 points)
If the Forecast for the previous month is 16 and the actual demand is 17. What is the Exponential Smoothing forecast for the next month using a smoothing constant (alpha) of 0.4?
Question 14 options:
| 14.4 | |
| 14.2 | |
| 14.6 | |
| 12.8 | |
| 16.2 |