Question: Question 13 (6 points) Critical path is the longest path through the activity network that allows for the completion of all project-related activities. True False
Question 13 (6 points) Critical path is the longest path through the activity network that allows for the completion of all project-related activities. True False Question 14 (6 points) At the beginning of the project risk cost is low. True False Question 15 (5 points) Activities should last at least 1 year in order to considered "Project" True False
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
