Question: Question 13 A project's WACC has been incorrectly overstated by the managers of a firm What effect will this have on the risk and the
Question 13 A project's WACC has been incorrectly overstated by the managers of a firm What effect will this have on the risk and the NPV of the project? Risk will be overstated, NPV will be understated. Risk will be overstated, NPV will be overstated. Risk will be understated, NPV will be understated. Risk will be understated, NPV will be overstated