Question: question 13 affect the completion date? 13. Here is a network with the activity times shown in days: B03 D(5) F14) ACT C14) EC2) a.

question 13 affect the completion date? 13. Here

question 13

affect the completion date? 13. Here is a network with the activity times shown in days: B03 D(5) F14) ACT C14) EC2) a. Find the critical path. b. The following table shows the normal times and the crash times, along with the asso- ciated costs for each activity. Crash Time Normal Cost Crash Cost Activity A B Normal Time 7 2 6 1 3 4 C D E F G 5 2 4 4 1 2 4 $7,000 5,000 9,000 3,000 2.000 4.000 5,000 $ 8.000 7.000 10,200 4.500 3,000 7.000 8.000 5