Question: question 13 for question 14 here are the answer choices a.16.8 b.9.13 c.10.43 d.7.43 A process has 15 tasks. The total amount of time to
A process has 15 tasks. The total amount of time to complete all tasks is 45 minutes. The longest task takes 4 minutes, the shortest task takes 2.5 minutes. What is the maximum throughput if the company operate 2 shifts per day, 8 hour per shifts and workers has one 30 -minute meal break and two 15 -minute mid-shift breaks? 22 units 336 units 19 units 384 units Question 14 10 pts A subassembly has the following precedence diagram. The number above each task represents the time needed to complete each task in minutes. The company operates for one shift per day, 8 hour per shift and workers have a 30 -minute lunch break and two 15 -minute shift break. The desired throughput per shift is 46 . What is the cycle time given such throughput