Question: question 13 for question 14 here are the answer choices a.16.8 b.9.13 c.10.43 d.7.43 A process has 15 tasks. The total amount of time to

question 13  question 13 for question 14 here are the answer choices a.16.8
for question 14 here are the answer choices
a.16.8
b.9.13
c.10.43
d.7.43

A process has 15 tasks. The total amount of time to complete all tasks is 45 minutes. The longest task takes 4 minutes, the shortest task takes 2.5 minutes. What is the maximum throughput if the company operate 2 shifts per day, 8 hour per shifts and workers has one 30 -minute meal break and two 15 -minute mid-shift breaks? 22 units 336 units 19 units 384 units Question 14 10 pts A subassembly has the following precedence diagram. The number above each task represents the time needed to complete each task in minutes. The company operates for one shift per day, 8 hour per shift and workers have a 30 -minute lunch break and two 15 -minute shift break. The desired throughput per shift is 46 . What is the cycle time given such throughput

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!