Question: Question 13 (Mandatory) (1 point) Saved Consider the following table of activities A through E in which A is the start node and E is
Question 13 (Mandatory) (1 point)
Saved
Consider the following table of activities A through E in which A is the start node and E is the stop node. Assume the project starts on Monday, May 4, 2020 and no work is done on weekends (Saturday and Sunday).
| Activity | Duration (days) | Predecessor |
| A | 5 | -- |
| B | 5 | A |
| C | 10 | A |
| D | 4 | A |
| E | 5 | B, C, D |
On a piece of scratch paper, draw the early-start Gantt Chart for the table above. What is the early-start date for activity D?
Question 13 options:
|
| Wednesday, May 13, 2020 |
|
| Sunday, May 10, 2020 |
|
| Tuesday, May 12, 2020 |
|
| Saturday, May 9, 2020 |
|
| Monday, May 11, 2020 |