Question: QUESTION 14 When there is variability in activity times, a more accurate estimate of the time required to complete a task can be calculated using

QUESTION 14

  1. When there is variability in activity times, a more accurate estimate of the time required to complete a task can be calculated using the most optimistic, most likely, and most pessimistic times.

    True

    False

2 points

QUESTION 15

  1. A Gantt chart is a diagram that clarifies the interdependency of activities (which tasks must be completed before other tasks may begin) and shows where the critical path lies.

    True

    False

2 points

QUESTION 16

  1. According to Goldratt, three phenomena tend to bias the expected completion time of projects: inflated time estimates, activity time variability with path interdependencies, and resource constraints.

    True

    False

2 points

QUESTION 17

  1. Projects are different from other types of operations because each project has a clear beginning and end.

    True

    False

2 points

QUESTION 18

  1. Control limits on a statistical process control chart are the upper and lower boundaries of a product's acceptability to the customer.

    True

    False

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!