Question: QUESTION 14 When there is variability in activity times, a more accurate estimate of the time required to complete a task can be calculated using
QUESTION 14
-
When there is variability in activity times, a more accurate estimate of the time required to complete a task can be calculated using the most optimistic, most likely, and most pessimistic times.
True
False
2 points
QUESTION 15
-
A Gantt chart is a diagram that clarifies the interdependency of activities (which tasks must be completed before other tasks may begin) and shows where the critical path lies.
True
False
2 points
QUESTION 16
-
According to Goldratt, three phenomena tend to bias the expected completion time of projects: inflated time estimates, activity time variability with path interdependencies, and resource constraints.
True
False
2 points
QUESTION 17
-
Projects are different from other types of operations because each project has a clear beginning and end.
True
False
2 points
QUESTION 18
-
Control limits on a statistical process control chart are the upper and lower boundaries of a product's acceptability to the customer.
True
False