Question: Question 15 1 pts Setup Cost = $760 per setup Holding cost = $0 per unit per week Lead Time = 1 Week Safety Lead

Question 15 1 pts Setup Cost = $760 per setup

Question 15 1 pts Setup Cost = $760 per setup Holding cost = $0 per unit per week Lead Time = 1 Week Safety Lead Time = 1 Week Scrap Allowance = 7.6% Lot Size = LFL (Lot-for-Lot) Week 1 N 3 4 5 6 7 8 9 10 11 12 Gross Requirements 466 552 687 646 651 611 518 574 659 690 689 609 459 Scheduled Receipts Beg. Inventory 811 Net Requirements Ending Inventory Planned Order Receipts Planned Order Releases What are your Planned Order Releases for Week 5? Round up to a whole unit