Question: Question 15 1.4 points Save Answer A project is expected to last 10 weeks. 5 weeks in, the project has an Earned Value of

Question 15 1.4 points Save Answer "A project is expected to last

Question 15 1.4 points Save Answer "A project is expected to last 10 weeks. 5 weeks in, the project has an Earned Value of $2000 and Planned Value of $3000. Based on this performance, what is the Schedule Forecast of the project? 15 weeks 10 weeks 5 weeks 20 weeks