Question: QUESTION 15 Find a workforce plan using the level strategy that allows for no delay in service. Overtime can be used and undertime should be

QUESTION 15

  1. Find a workforce plan using the level strategy that allows for no delay in service. Overtime can be used and undertime should be minimized.
    1 2 3 4
    Forecasted Demand 3400 5200 6500 4300
    Workforce Level
    Undertime hours
    Overtime hours
    Utilized time hours
    # of Hires
    # of Layoffs
    Utilized time cost
    Undertime cost
    Overtime Cost
    Hiring cost
    Layoff cost
    What is the workforce level in each quater for this plan using level strategy?

    16

    14

    12

    17

1 points

QUESTION 16

  1. What is the undertime hours in the 2nd quater?

    1300

    400

    800

    600

1 points

QUESTION 17

  1. What is the overtime hours in the 3rd quater?

    0

    800

    900

    600

1 points

QUESTION 18

  1. What is the utilized time hours in the 1st quater?

    3400

    5600

    1200

    6800

1 points

QUESTION 19

  1. What is the hire or layoff plan in the 1st quater?

    layoff 2

    no hire or layoff

    hire 14

    hire 7

1 points

QUESTION 20

  1. What is the hire or layoff plan in the 3rd quater?

    hire 7

    no hire or layoff

    hire 14

    layoff 2

1 points

QUESTION 21

  1. What is the undertime cost in the 2nd quater?

    $8000

    $24000

    $6000

    $18000

1 points

QUESTION 22

  1. What is the overtime cost in the 3rd quater?

    24000

    27000

    0

    19000

1 points

QUESTION 23

  1. What is the total cost of this level strategy?

    552000

    486000

    526500

    490500

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!