Question: Question 15 SUPER ONE BASE ELECTRONIC INSERT On Hand inventary shows HAND Super One Base Electronic Given the above BOM and a master production schedule

Question 15 SUPER ONE BASE ELECTRONIC INSERT On
Question 15 SUPER ONE BASE ELECTRONIC INSERT On Hand inventary shows HAND Super One Base Electronic Given the above BOM and a master production schedule for the SUPER ONE below. LT - I week, lot size - 25 Week 1 Week 2 Week 3 20 Week 4 Gross req On Hand Net Reg Plan Rec Plan Rel Gross requirements for the Electronic Insert would show up in week(s): 2&3 1&3 2,3.& 4 1& 2 3& 4