Question: Question 16 (4 points) All projects (A to G) are 7-year projects. NPV = Net present value. IRR = internal rate of return. MIRR =

Question 16 (4 points)

All projects (A to G) are 7-year projects. NPV = Net present value. IRR = internal rate of return. MIRR = modified internal rate of return. PI = profitability index.

Project A Project B Project C Project D Project E Project F Project G
NPV= $4,711 ($711) ($657) $334 $9,842 $7,360 ($3,224)
IRR= 44.51% 5.47% 8.06% 12.98% 22.56% 17.19% 5.47%
MIRR= 25.23% 7.50% 8.97% 11.57% 16.26% 13.70% 7.50%
PI= 2.178 0.822 0.945 1.028 1.394 1.294 0.871

Criteria Project_A Project_B Project_C Project_D Project_E Project_F Project_G
NPV= $14,154 $77,992 $29,515 $11,564 ($8,849) $26,514 $30,022
IRR= 28.66% 20.33% 19.72% 45.52% 9.03% 16.40% 16.05%
MIRR= 17.28% 14.35% 12.86% 22.76% 9.53% 11.97% 12.45%
PI= 1.57 1.31 1.20 2.16 0.97 1.13 1.17

The discounting rate (r) is 10%.

Which of the following 10 statements are true (there are several, select all that are correct). Consider each statement on its own separate from the others listed:

Question 16 options:

If projects A & D are mutually exclusive, projects B and C are also mutually exclusive and projects E and F are also mutually exclusive (all others are independent), under the IRR rule projects A, C, and E should be undertaken

If projects A & D are mutually exclusive, projects B and C are also mutually exclusive and projects E and F are also mutually exclusive (all others are independent), under the IRR rule projects A, D, E, and E should be undertaken

If all projects are mutually exclusive, under the NPV rule only project E should be taken

If all projects are mutually exclusive, under the NPV rule projects A, D, E and F should be taken

If all projects are independent, under the IRR rule, all projects should be taken

If projects A & D are mutually exclusive, projects B and C are also mutually exclusive and projects E and F are also mutually exclusive (all others are independent), under the IRR rule projects A, and E should be undertaken

If all projects are independent, under the NPV rule, projects A, D, E, and F should be taken

If only projects B and C are mutually exclusive, under the NPV rule only project A should be taken

If all projects are mutually exclusive, under the IRR rule only project E should be taken

If projects A & B are mutually exclusive, projects C and D are also mutually exclusive and projects F and G are also mutually exclusive (all others are independent), under the MIRR rule all projects should be undertaken

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Finance Questions!