Question: Question 16 A lag can only be applied when there is a finish-to-start activity relationship. True False False, a lag, which is a delay in

Question 16 A lag can only be applied when there is a finish-to-start activity relationship. True False False, a lag, which is a delay in the successor activity, can be found on all activity relationship types and not just the ones that are finish-to-start. 2.6 Question 17 What are examples of project scheduling presentation styles. Choose all tha Barber Curve Chart Network Diagram Gantt Chart Milestone Chart