Question: question #16-NPV when project would you select based on NPVs assuming the same10% dscount rate for both? Project A requres an inital outay of Stooo

 question #16-NPV when project would you select based on NPVs assuming

question #16-NPV when project would you select based on NPVs assuming the same10% dscount rate for both? Project A requres an inital outay of Stooo and provides an annual income of $500 for 3 years Project 8 requires an initial outlay of $2.000 and yields an annual income of $900 for 3 years Multiple Choice Project A Project B Project A or B is indifterent