Question: Question 17 (1 point) Consider a project with the following information. Activity Immediate predecessors Normal time Crash cost per Crash time period A -
Question 17 (1 point) Consider a project with the following information. Activity Immediate predecessors Normal time Crash cost per Crash time period A - 10 8 $180 B C A A 12 11 $300 11 10 $150 D - 26 8 $220 E B, C What is the total cost of crashing the project by 1 time unit(s)? 5 3 $250