Question 17 (1 point) The following represents a project with known activity times. All times are in weeks. Immediate Time Activity Predecessor(weeks) A B 5 3 C A 5 D B 5 E C, D 10 LL F B 5 What is the minimum possible time required for completing the project (round it to the nearst whole number)? Your Answer