Question: Question 17 Complete the below master production schedule. Knowing that lot size is 350 and beginning inventory is 150 units, what is the value of
Question 17 Complete the below master production schedule. Knowing that lot size is 350 and beginning inventory is 150 units, what is the value of projected available in period 5? 2 4 5 6 1 150 50 3 50 70 Period Forecast Customer orders 50 110 100 30 70 80 60 50 Projected available MPS O 170 units 280 units 180 units 40 units