Question: QUESTION 18 Process Design using small lot size could increase the ordering costs and the shipping costs. True False 1 points QUESTION 19 In a
QUESTION 18
Process Design using small lot size could increase the ordering costs and the shipping costs.
True
False
1 points
QUESTION 19
-
In a PERT chart, the Early Finish of a task is always equal to the Early Start of the following task(s).
True
False
1 points
QUESTION 20
The four building blocks of JIT are: product design, process design, personnel/organizational elements, and planning and control.
True
False
1 points
QUESTION 21
In a broad sense, JIT is not identical to lean production.
True
False
1 points
QUESTION 22
The Critical PATH in a PERT chart shows the shortest path from the start to the end of a project.
True
False
1 points
QUESTION 23
A Kanban card is used to signal that work is ready to be moved to the next station.
True
False
1 points
QUESTION 24
Continuous Improvement (Kaizen) is a Japanese methodology that is used mainly for the production lines
True
False
1 points
QUESTION 25
Just In Time Systems work for either a Pull or a Push system
True
False
1 points
QUESTION 26
Both reliability and serviceability are quality dimension for a service
True
False