Question: Question 18 When a project manager needs to reduce the length of a project, they need to crash items that are on the O Slack
Question 18

When a project manager needs to reduce the length of a project, they need to crash items that are on the O Slack Central Vein O Shortest Path O Least Common Multiple O Critical Path