Question: Question 19 (1 point) The following represents a project with four activities. All times are in weeks. Most Immediate Optimistic Likely Pessimistic Activity Predecessor Time

Question 19 (1 point) The following represents a
Question 19 (1 point) The following represents a project with four activities. All times are in weeks. Most Immediate Optimistic Likely Pessimistic Activity Predecessor Time Time Time 9 10 14 - 888 DA 6 9 18 DB 5 11 17 What is the minimum expected completion time for the project (please round off to two decimal digits)