Question: Question 19 (5 points) Compute the takt time for a service system that intended to perform a standardized service. The system will have a total

Question 19 (5 points) Compute the takt time for
Question 19 (5 points) Compute the takt time for a service system that intended to perform a standardized service. The system will have a total work time of 348 minutes per day, including four 15-minute breaks, and an hour for lunch. The service system must process 92 jobs a day. (Round your answer to 2 decimal places.) Your Answer: Answer units