Question: Question 1(Mandatory)(1 point) Saved Within project management many different documents are produced. Which of the following documents would be the appropriate one to define the
Question 1(Mandatory)(1 point)
Saved
Within project management many different documents are produced.
Which of the following documents would be the appropriate one to define the processes to monitor and control risks?
Question 1 options:
Expert judgement interview notes | |
Risk registry | |
Risk management plan | |
Minutes to risk workshop planning meetings |
Question 2(Mandatory)(1 point)
Saved
The environment that a project operates in changes throughout the project lifecycle, which results in our understanding of project risks also evolving during a project's lifecycle.
As such, which of the following statements represents a valid opportunity to perform a risk assessment on the project?
Question 2 options:
At the start of the project | |
When a scope change to the project occurs | |
Before a major decision point | |
All of the above |
Question 3(Mandatory)(1 point)
Saved
Risks can occur at any point in a project's lifecycle; the risks that are encountered early on in the project are often different from those that can be encountered at later stages of the project.
However, in general, risk events that occur (or are discovered) later in the project's lifecyle tend to have a greater impact on the project than those that occur earlier in the project's lifecycle.
Which of the following statements isnota valid potential explanation for this observation?
Question 3 options:
| |||
| |||
| |||
|
Question 4(Mandatory)(1 point)
Saved
When identifying risk, the PMBOK recommends examining each element of the project work breakdown structure (WBS) to determine what risk might be associated with that WBS item.
TRUE OR FALSE: Is it possible to also identify additional risks by examining the project assumptions and estimates?
Question 4 options:
| 1) True | |
| 2) False |
Question 5(Mandatory)(1 point)
Saved
After identifying project risks, the risk manager must determine the best strategy or strategies for dealing with the risks.
The four basic categories of risk strategies (for negative risks) identifed within the PMBOK and within this course are:
Question 5 options:
Technical, marketing, financial and human | |
Identification, quantification, response development and response control | |
Avoidance, transference, mitigation and acceptance | |
Avoidance, retention, control and deflection |
Question 6(Mandatory)(1 point)
Saved
Question 6 options:
(1) Execution phase and (2) Monitoring and Controlling phase | |
(1) Planning phase and (2) Execution phase | |
(1) Introduction phase and (2) Monitoring and Controlling phase | |
(1) Planning phase and (2) Monitoring and Controlling phase |
Question 7(Mandatory)(1 point)
Saved
Question 7 options:
Project management plan | |
Risk register | |
Stakeholder register | |
Enterprise environmental factors |
Question 8(Mandatory)(1 point)
Saved
There are many different ways that have been developed over the years to identify project risks.
The list below contains several examples of valid risk identification methods, and some items that are not.
From the list, select those thatarevalid risk identification methods.
Question 8 options:
| |||
| |||
| |||
| |||
| |||
| |||
|
Question 9(Mandatory)(1 point)
Saved
A risk management plan covers a number of different topics regarding risks.
However, what risk topic shouldnotbe covered by a risk management plan?
Question 9 options:
Roles and responsibilities for handling project risks | |
Timing of project risk management activities | |
The methodological approach used for risk management | |
Individual risks and potential responses to them |
Question 10(Mandatory)(1 point)
Saved
Question 10 options:
It is a RiskResponsibilityAssignmentMatrix (Risk RAM) | |
It is aRiskBreakdownStructure (RBS) | |
It is a Risk Impact Definition Table | |
It is a Stakeholder's Risk Tolerance Table |
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
