Question: Question 2 1 ( 1 point ) Assume that the normal duration of activity A is 2 3 days and that it can be shortened

Question 21(1 point)
Assume that the normal duration of activity A is 23 days and that it can be shortened to 13 for an added cost of $2200, the crash cost per day is,
Note:
1- Round your final answer to the nearest integer.
2- Do not include the $ symbol in your answer. For instance, if the crash cost per day is $56.76, just enter 57.