Question: Question 2 1 ( 1 point ) The WBS should be decomposed to a level that identifies individual work packages for A ) each person

Question 21(1 point)
The WBS should be decomposed to a level that identifies individual work packages
for
A) each person that planned the project.
B) each resource assigned to the project.
C) the level of detail specified by the customer.
D) each specific deliverable listed in the project scope document.
 Question 21(1 point) The WBS should be decomposed to a level