Question: Question 2 1 ( 1 point ) The WBS should be decomposed to a level that identifies individual work packages for A ) each person
Question point
The WBS should be decomposed to a level that identifies individual work packages
for
A each person that planned the project.
B each resource assigned to the project.
C the level of detail specified by the customer.
D each specific deliverable listed in the project scope document.