Question: QUESTION 2 1 A new development is planned for a community, but it is in watershed adjacent to the watershed served by the existing wastewater

QUESTION 21
A new development is planned for a community, but it is in watershed adjacent to the watershed served by the existing wastewater treatment plant. To transport the wastewater to the wastewater treatment plant, a lift station is needed to pump the wastewater over a ridge to an existing interceptor in the existing collection system. The interceptor has sufficient capacity for the estimated 4.6 MGD peak flow from the new development.
A. If the lift station designed for the development will have three identical pumps, then each pump will have a minimum capacity in gallons per minute of most nearly:
a)1,065
b)1,597
c)3,194
d)4,600
a)1065
b)1597
d)4600
q, c)3194
QUESTION 2 1 A new development is planned for a

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Civil Engineering Questions!