Question: Question 2 1 During a test on a 3 - m suppressed weir 9 0 0 m high, the head was maintained constant at 3

Question 21
During a test on a 3-m suppressed weir 900 m high, the head was maintained constant at 300 mm . in 36 seconds. 28.800 liters of
water were collected. What is the weir factor CW
A
Question 22
Assessmenc security
A rectangular contracted weir is 4.1 ft wide was used to measure the flow in the irrigation canal crest height is 1.1 ft and height of
water before the weir is 5 ft . Calculate the flow over the weir in ft3s.
Ad
-1
Grading
and
Extra Credit
Additional information
Refresh the assersmant 10.2
you sutmit an atteriph
Question 2 1 During a test on a 3 - m suppressed

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Civil Engineering Questions!