Which two common issues can have a negative impact on project productivity in the design-bidbuild method of project delivery?
waiting on the delivery of materials with long lead times
incorrect activity durations, which cause scheduling conflicts
excessive requests for information
change orders due to design and constructability issues
decreased productivity at the workplace
increased inspection times