Question: Question 2 ( 1 point ) Listen Once the project starts, it is necessary to keep track of actual cost and committed cost so that

Question 2(1 point)
Listen
Once the project starts, it is necessary to keep track of actual cost and committed cost so that they can be compared to the q,
A) total budgeted cost
B) cumulative budgeted cost
C) total cumulative fees
D) contract cumulating amount