Question 2 1 pts You are evaluating a project with an initial investment (at year 0) of $41,000 that will produce annual monetary benefits of $17,000 for each of the next 4 years, starting in year 1. A year after the project ends (at year 5), there is an abandonment cost of $27,000. If your firm's cost of capital is 9.00% per year, what is the net present value (NPV) of this project? $14,075.24 $-3,472.91 S-3,830.11 $0.00