Question: Question 2 10 pts Using the cost data for Project X and Project Y below, conduct a Present Worth Analysis to calculate the Present Worth
Question 2 10 pts Using the cost data for Project X and Project Y below, conduct a Present Worth Analysis to calculate the Present Worth of Project X at time over LCM years of the life of both X and Y. Given 10% per year interest rate. X Y First Cost -60,000 - 150,000 Annual Cost -12,000 -7,000 Salvage 5,000 80,000 Value Life 10 Infinity Present Worth of Project X is closest to which answer? -247,453 O-131,807 -186,665 O-214,510 Question 3 10 pts Using exactly the same information from Problem No. 1 above, calculate the Present worth of Project Y at 10% per year interest rate