Question: Question 2 15 Marks Let the following table represents the activities of a project to be implemented. When solving this question use the CPM method.

Question 2 15 Marks Let the following table
Question 2 15 Marks Let the following table represents the activities of a project to be implemented. When solving this question use the CPM method. Duration Immediate Predecessors Activity (Weeks) 10 8 - A 2 A 6 B, D 5 C, D 3 E, F a) Draw the network diagram. b) Determine ES, EF, LS, and LF for each activity. c) Determine the slacks of every activity. d) Determine the critical path. e) Determine the duration of the project. Answer ABCDEFG 4

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!