Question: Question 2 (15 points): For this question, look at the fifth column labeled Number of Resources Required (ignore the fourth column labeled Specialized Resource Required).
Question 2 (15 points): For this question, look at the fifth column labeled Number of Resources Required (ignore the fourth column labeled Specialized Resource Required).
Assume that each task can be worked on by any resource, but different tasks require a different number of resources. For example, task B requires 4 people to work on it. How many resources do you need to have available within the team to complete the project without any resource related delays? In how many days will you complete the project? Show your work.
Note Said differently, how many resources would be required to complete the project in the shortest duration.

Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
