Question: Question 2 ( 2 0 marks ) A leading information technology company has a project involving the installation of a computer system involving eight activities.

Question 2(20 marks)
A leading information technology company has a project involving the installation of a
computer system involving eight activities. The following table lists immediate
predecessors, activity times in weeks as well as other relevant information about the
activities.
Activity Immediate
predecessor
activity
Normal
duration
(weeks)
Normal
cost
Crash
time
(weeks)
Cost if
crashed
A -3 N$9001 N$1700
B -6 N$20003 N$4000
C A 2 N$5001 N$1000
D B, C 5 N$18003 N$2400
E D 4 N$15003 N$1850
F E 3 N$30001 N$3900
G B, C 9 N$80004 N$9800
H F, G 3 N$10002 N$2000
FACULTY OF COMMERCE, MANAGEMENT AND LAW
OLD CURRICULUM MODULES
Page 17 of 18
Required
Marks
Sub-
total Total
2.1
Draw a network diagram based on the normal times given,
illustrating the critical path routes and determine the normal cost and
duration to complete the project.
66
2.2 Determine the earliest starting time and the latest starting time of
each activity. 814
2.3
Assuming that the project has to be completed in 16 weeks, what
crashing decisions do you recommend to meet the desired
completion time at the least possible cost? Work through the
network and attempt to make the crashing decisions by inspection.
620

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!