Question: QUESTION 2 ( 2 0 Marks ) Anthony Adams is building a double storey house and has identified eleven activities that are required to complete
QUESTION
Marks
Anthony Adams is building a double storey house and has identified eleven activities that are required to complete this important project. He has calculated early and late start times and early and late finish times but spilt tea all over his printout. Use the remaining information to reconstruct the table for Anthony Adams
tableActivityPredecessor,Duration,Early Start,Late Start,Early Finish,Late FinishABACADBEECFEGDHGIGJFKHI,J
QUESTION
Marks
Inefficiencies in project communication can have serious effect on the chance of success. Give a critical discussion of the importance of communication in project management.