Question: Question 2 2 ( 1 point ) Saved Listen What are the planned order receipts and planned order releases of Item J at period 4

Question 22(1 point)
Saved
Listen
What are the planned order receipts and planned order releases of Item J at period 4?
46 and 63
63 and 67
43 and 63
63 and 63
67 and 63
Question 23(Bonus)(1 point)
Saved
What is the net requirement of item J at period 2?
63
67
46
21