Question: Question 2 2 . 1 The soil volumes on a road construction project are as follows: Loose volume = 3 6 2 m 3 Compacted

Question 2
2.1 The soil volumes on a road construction project are as follows:
Loose volume =362m3
Compacted volume =255m3
Bank volume =290m3
(a) Define the term "swell" for earthworks volume calculations and provide an example of a situation in which swell could occur.
(2)
(b) Calculate the following factors (to two decimal places):
Bulking factor
Shrinkage factor
Compaction factor
(2)
(2)
(2)
Question 2 2 . 1 The soil volumes on a road