Question: Question 2 2 2 . 5 p t s Dexter decides to hire Francis to build an extension onto his house. They enter into a

Question 22
2.5pts
Dexter decides to hire Francis to build an extension onto his house. They enter into a contract on March 1st, and the deadline for completing the extension is May 1st. Given the nature and size of the project, the extension will take at least one week to complete once the work on it has started.
The Dexter-Francis contract states that "time is of the essence" because Dexter is having family over from May 2nd to May 12th, and Dexter needs the extra space for them to stay. Even though the deadline gets closer and closer, Francis never starts construction. Finally, on April 27th, Dexter declares Francis to have breached the contract. Francis argues that Dexter cannot declare a breach yet. Who is correct?
Dexter is correct only if Francis has made no effort to contact him and notify him that he will be unable to complete the construction.
Francis is correct because Dexter cannot declare a breach of contract until the actual deadline has passed.
Francis is correct because he could not be reasonably expected to complete the construction in the time frame required by the contract - or, alternatively, at this point in time Francis is entitled to a Nachfrist notice.
Dexter is correct because he can declare an anticipatory breach if it is clear that Francis will not meet the deadline.
Dexter is correct because Francis automatically breached the contract by failing to complete the work by April 15.
 Question 22 2.5pts Dexter decides to hire Francis to build an

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!