Question: QUESTION 2 ( 2 4 marks ) ( a ) A construction project involves the activities listed in Table 2 . 1 . Information on
QUESTION marks
a A construction project involves the activities listed in Table Information on the immediately preceding activity IPA normal duration and cost, as well as crash duration and cost for each activity are also provided in the table. The indirect cost for the project is $ per month.
i marks Draw the activityonarrow network diagram for this project; identify the critical path and project duration based on normal activity durations.
ii marks If the project team wants to shorten the project duration by months with the least increase in direct costs, what is the total project cost and critical path as a result of the shortening?
Table List of activities for project in Question a
tableActivityIPA,tableNormal DurationmonthstableNormalDirect CosttableCrash DurationmonthstableCrashDirect CostA$$
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock