Question: Question 2 : [ 2 5 Marks ] On a day, six cars are awaiting the washing and waxing services at a car garage. Both

Question 2: [25 Marks]
On a day, six cars are awaiting the washing and waxing services at a car garage. Both the washing and waxing processes can serve one car only at a time.
The following table shows the times in minutes required to complete each of the six cars in the washing and waxing processes. Each car must follow the same sequence, beginning with the washing process and moving to the waxing process.
\table[[,a,b,c,d,e,f],[Washing,13,18,16,18,17,14],[Waxing,15,12,17,18,11,16]]
a. Determine a sequence that will minimize the makespan time.
[10 marks]
b. Construct a chart of the resulting sequence, and find the optimal makespan, Washing process's idle time, Waxing process's idle time, and the total idle time of this two-machine flow shop.
[15 marks]
 Question 2: [25 Marks] On a day, six cars are awaiting

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!