Question: Question 2 2 Using PERT, Mohammad determined that the expected project completion time for constructing the Hospital building is 2 2 months, and the project

Question 22Using PERT, Mohammad determined that the expected project completion time for constructing the Hospital building is 22 months, and the project variance is 36. What is the probability that the project will be completed in 16 months?