Question: Question 2 [ 20 marks ] Given the information of a project in the Table 2 below. Note that the project is completed when activity
Question 2 [20 marks]
Given the information of a project in the Table 2 below. Note that the project is completed when activity F and G are completed.
Table 2
| Activity | Dependency | Time (months) |
| A | - | 4 |
| B | - | 6 |
| C | A | 2 |
| D | A | 6 |
| E | C,B | 3 |
| F | C,B | 3 |
| G | D,E | 5 |
- In many practical situations, activity times are not known exactly. Explain how you may deal with situations where activity times are uncertain. [4]
[Note: Answer must not exceed more than 8 lines using 11pt font]