Question: Question 2: (20 marks) Suppose you are offered an internship position after your satisfactory interview performance (in Question 1). As an intern, you are asked
Question 2: (20 marks)
Suppose you are offered an internship position after your satisfactory interview performance (in Question 1). As an intern, you are asked to study about inventory problems and to prepare a material requirement plan (MRP) for a new product T which structure and other relevant data are given below:
| Component/Subassembly | Number Required | Lead Time |
| Subassembly A | 3 | 2 weeks |
| Component B | 4 | 2 weeks |
|
|
|
|
| Subassembly A | Number Required | Lead Time |
| Component B | 2 | 2 weeks |
| Component C | 5 | 1 week |
Subassembly A and Components B and C are purchased from external suppliers.
Both Components B and C are also sold to customers. A particular customer of Component B requires 140 units in week 2 and 50 units in week 5 while another customer of Component C needs 300 in week 3 and 200 in week 6. The beginning inventory of Subassembly A is 200 units, the beginning inventories of Components B and C are 600 and 100 units, respectively. There is no inventory of product T.
The Master Production Schedule (MPS) data of product T as well as the lot size, lead time, safety stock requirement and minimum order quantity for Subassembly A, Components B and C are shown in the following worksheets.
MRP worksheet
| MPS Data for product T | Lead Time: 1 week | ||||||||
| Week number | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | |
| Gross Requirements |
|
|
|
| 90 | 80 |
| 20 | |
| Planned order releases |
|
|
| 90 | 80 |
| 20 |
| |
| Subassembly A |
|
|
|
| Lot size: | 100 | ||||||||
| Minimum order quantity: | 200 | units |
|
| Lead time: | 2 | weeks | |||||||
| Immediate Parent(s): |
| Safety stock: | 100 | units | ||||||||||
| Week number |
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | |||||
| Gross Requirements |
|
|
|
|
|
|
|
| ||||||
| Scheduled Receipts |
|
|
|
|
|
|
|
| ||||||
| Projected on hand | 200 |
|
|
|
|
|
|
|
| |||||
| Net Requirements |
|
|
|
|
|
|
|
|
| |||||
| Planned order receipts |
|
|
|
|
|
|
|
|
| |||||
| Planned order releases |
|
|
|
|
|
|
|
| ||||||
- Determine the planned order releases for Subassembly A. Present your answer with the following table in your Answer File and the whole worksheet showing the steps.
| Week number |
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | |
| Planned order releases |
|
|
|
|
|
|
|
| ||
(3 marks)
Answer Here:
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts