Question: Question 2 (27 marks) The following data has been extracted from Namibia Construction Company (NCC) a company that undertakes various building projects around Namibia. Activity
Question 2 (27 marks)
The following data has been extracted from Namibia Construction Company (NCC) a company that undertakes various building projects around Namibia.
| Activity | Previous activity | Normal time (days) | Normal costs N$ | Crash time | Crash costs N$ | Cost slope |
| A | - | 13 | 20 000 | 12 | 25 000 | ? |
| B | - | 13 | 15 000 | 10 | 18 000 | ? |
| C | A | 12 | 10 000 | 12 | 10 000 | ? |
| D | A | ? | 12 000 | 8 | 12 000 | ? |
| E | A | 10 | 8 000 | 8 | 11 000 | ? |
| F | E | 5 | 6 000 | 5 | 6 000 | ? |
| G | D, F | 7 | 4 000 | 5 | 5 000 | ? |
| H | B, C | 6 | 5 000 | 5 | 6 500 | ? |
| I | G, H | 9 | 8 000 | 8 | ? | 3 000 |
The duration of activity D cannot be determined accurately. The estimates are as follows:
- Most likely 8 days
- Optimistic time 6 days
- Pessimistic time 10 days
You have been hired as the management accountant of NCC and you have been tasked to assist the management in various calculations.
| Requirement | Mark | ||
| Sub- total | Total | ||
| 2.1 | Draft a network diagram for the project. | 10 | 10 |
| 2.2 | Identify the different paths and indicate which one is the critical path. | 6 | 16 |
| 2.3 | Calculate the normal cost of the project. | 2 | 18 |
| 2.4 | Calculate the earliest starting time of the event that precedes activity H. | 2 | 20 |
| 2.5 | Calculate the latest starting time of the event that precedes activity G. | 2 | 22 |
| 2.6 | Calculate the crash cost for activity I. | 2 | 24 |
| 2.7 | Calculate the total cost if the project has to be completed in 41 days. | 3 | 27 |
| Note: Show all the necessary workings or steps that are required to reach the answer. Marks are available for these. |
| ||
| Total | 27 | ||