Question: QUESTION 2 ( 3 0 marks ) Consider the project with the following estimates for activity times and precedence relationships: table [ [ Activity
QUESTION marks
Consider the project with the following estimates for activity times and precedence relationships:
tableActivitytableOptimisticTimetableMostLikely TimetablePessimisticTimetableImmediatePredecessorsABCADBEBFC DGD EHF
a Calculate the expected time for each activity marks
b What is the expected duration of the project? marks
c What is the project variance? marks
d If the deadline of the project is days, what is the probability of finishing the project on time? marks
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
